Item Description Contract $ % this claim This claim % to date Progress Claimed to date Previous Remaining 1 โ PROJECT MANAGEMENT & PRELIMINARIES 1.1 PM, Supervision, Admin & Overheads 243,432.00 %36,514.80 15.0% 36,514.80 0.00 206,917.20 1.2 Site Facilities 25,725.00 %0.00 0.0% 0.00 0.00 25,725.00 2 โ SUPPLY 2.1 Contractor Supply as per SOW 1,001,335.37 %300,400.61 30.0% 300,400.61 0.00 700,934.76 2.2 Stand Pipe Opt 1 316SS SCH 40 (x2) (2 ea @ 18,582.00) 37,164.00 %11,149.20 30.0% 11,149.20 0.00 26,014.80 2.3 Stand Pipe Off Take Tee 560-110 (x2) (2 ea @ 8,390.00) 16,780.00 %5,034.00 30.0% 5,034.00 0.00 11,746.00 2.4 Additional Drain Off Take 560-355V 7,580.00 %2,274.00 30.0% 2,274.00 0.00 5,306.00 3 โ MOBILISATION / DEMOBILISATION 3.1 Mobilisation 76,510.72 %11,476.61 15.0% 11,476.61 0.00 65,034.11 3.2 Demobilisation 54,367.72 %0.00 0.0% 0.00 0.00 54,367.72 3.3 Freight of Equipment Return 71,064.00 %0.00 0.0% 0.00 0.00 71,064.00 4 โ SITE INSTALLATION WORKS 4.1 Unloading of Pipe โ 58 trucks (58 trucks @ 1,468.55) 85,176.00 %0.00 0.0% 0.00 0.00 85,176.00 4.2 3,000m of 560 PN8 PE100 SDR21 (3000 m @ 16.61) 49,826.70 %0.00 0.0% 0.00 0.00 49,826.70 4.3 14,800m of 560 PN6.3 PE100 SDR26 (14800 m @ 20.14) 298,145.40 %0.00 0.0% 0.00 0.00 298,145.40 5.0 3,200m of 560 PN10 PE100 SDR21 (3200 m @ 16.99) 54,362.70 %0.00 0.0% 0.00 0.00 54,362.70 4.4 750m of 355 PN8 PE100 SDR17 (750 m @ 12.20) 9,147.60 %0.00 0.0% 0.00 0.00 9,147.60 4.5 Road Crossings x 10 (10 ea @ 10,859.52) 108,595.20 %0.00 0.0% 0.00 0.00 108,595.20 4.6 ARV Tie In's 560 62,130.60 %0.00 0.0% 0.00 0.00 62,130.60 4.7 Flush Water Tie In 6,293.70 %0.00 0.0% 0.00 0.00 6,293.70 4.8 Earth Mounding 55,692.00 %0.00 0.0% 0.00 0.00 55,692.00 4.9 Flow Metres / Actuated Valve / Scour Drain Tee 39,138.75 %0.00 0.0% 0.00 0.00 39,138.75 5.1 Install 2x Standpipe (2 ea @ 10,702.13) 21,404.25 %0.00 0.0% 0.00 0.00 21,404.25 6 โ OTHER 6.1 Cost Associated with Pre-Contract Legal 20,000.00 %20,000.00 100.0% 20,000.00 0.00 0.00 6.2 Survey 28,576.80 %0.00 0.0% 0.00 0.00 28,576.80 6.3 Freight of Pipe โ 58 Trailers Perth (58 trailers @ 7,182.00) 416,556.00 %0.00 0.0% 0.00 0.00 416,556.00 TOTALS 2,789,004.51 13.9% 386,849.22 13.9% 386,849.22 0.00 2,402,155.29