โ€น  Back to Shark Bay hub
Progress Claim Builder โ— not saved to the file yet
Type each line's % for this claim. Claimed / previous / this-claim / remaining all compute live. Click ๐Ÿ’พ Save claim file when done โ€” the data is stored inside this file, so the next person who opens it (SharePoint) sees everything.
PROGRESS CLAIM
Bitterns Recycling Field Piping Installation ยท DTL-PRJ0072
From
DTL (WA) Pty Ltd
2/28 Horus Bend, Bibra Lake WA 6163
ABN: 45 677 646 454
To
Shark Bay Resources Pty Ltd
ABN: 88 079 088 636
accounts@salt.com.au
References
PO-182113 ยท SBS10627
Job DTL-PRJ0072
Terms: 30 D F-I-M-E
CLAIM 001
Date Period
Original contract (ex GST)
$2,789,005
Claimed to date
$386,849
13.9% of contract
Remaining to claim
$2,402,155
86.1% of contract
Previously claimed
$0
THIS CLAIM (ex GST)
$386,849.22
GST 10%
$38,684.92
THIS CLAIM (incl GST)
$425,534.14
Contract progress โ€” claimed $386,849remaining $2,402,155
13.9% claimed
ItemDescriptionContract $% this claimThis claim% to dateProgressClaimed to datePreviousRemaining
1 โ€” PROJECT MANAGEMENT & PRELIMINARIES
1.1PM, Supervision, Admin & Overheads243,432.00%36,514.8015.0%
36,514.800.00206,917.20
1.2Site Facilities25,725.00%0.000.0%
0.000.0025,725.00
2 โ€” SUPPLY
2.1Contractor Supply as per SOW1,001,335.37%300,400.6130.0%
300,400.610.00700,934.76
2.2Stand Pipe Opt 1 316SS SCH 40 (x2) (2 ea @ 18,582.00)37,164.00%11,149.2030.0%
11,149.200.0026,014.80
2.3Stand Pipe Off Take Tee 560-110 (x2) (2 ea @ 8,390.00)16,780.00%5,034.0030.0%
5,034.000.0011,746.00
2.4Additional Drain Off Take 560-355V7,580.00%2,274.0030.0%
2,274.000.005,306.00
3 โ€” MOBILISATION / DEMOBILISATION
3.1Mobilisation76,510.72%11,476.6115.0%
11,476.610.0065,034.11
3.2Demobilisation54,367.72%0.000.0%
0.000.0054,367.72
3.3Freight of Equipment Return71,064.00%0.000.0%
0.000.0071,064.00
4 โ€” SITE INSTALLATION WORKS
4.1Unloading of Pipe โ€” 58 trucks (58 trucks @ 1,468.55)85,176.00%0.000.0%
0.000.0085,176.00
4.23,000m of 560 PN8 PE100 SDR21 (3000 m @ 16.61)49,826.70%0.000.0%
0.000.0049,826.70
4.314,800m of 560 PN6.3 PE100 SDR26 (14800 m @ 20.14)298,145.40%0.000.0%
0.000.00298,145.40
5.03,200m of 560 PN10 PE100 SDR21 (3200 m @ 16.99)54,362.70%0.000.0%
0.000.0054,362.70
4.4750m of 355 PN8 PE100 SDR17 (750 m @ 12.20)9,147.60%0.000.0%
0.000.009,147.60
4.5Road Crossings x 10 (10 ea @ 10,859.52)108,595.20%0.000.0%
0.000.00108,595.20
4.6ARV Tie In's 56062,130.60%0.000.0%
0.000.0062,130.60
4.7Flush Water Tie In6,293.70%0.000.0%
0.000.006,293.70
4.8Earth Mounding55,692.00%0.000.0%
0.000.0055,692.00
4.9Flow Metres / Actuated Valve / Scour Drain Tee39,138.75%0.000.0%
0.000.0039,138.75
5.1Install 2x Standpipe (2 ea @ 10,702.13)21,404.25%0.000.0%
0.000.0021,404.25
6 โ€” OTHER
6.1Cost Associated with Pre-Contract Legal20,000.00%20,000.00100.0%
20,000.000.000.00
6.2Survey28,576.80%0.000.0%
0.000.0028,576.80
6.3Freight of Pipe โ€” 58 Trailers Perth (58 trailers @ 7,182.00)416,556.00%0.000.0%
0.000.00416,556.00
TOTALS2,789,004.5113.9%386,849.2213.9%386,849.220.002,402,155.29

Variations / Additional Claims

none this claim
Claim register โ€” claimed vs remaining
ClaimPeriodThis claim ex GSTCumulative% of contractRemaining
0011386,849386,84913.9%2,402,155
002 โ€” this claim488,798875,64731.4%1,913,357
Submitted for DTL (WA) Pty Ltd
Signature โ€” sign on screen
Name:
Title:
Date:
Assessed / approved โ€” Shark Bay Resources Pty Ltd
Signature โ€” sign on screen
Name:
Date:
DTL (WA) Pty Ltd ยท ABN 45 677 646 454 ยท Dewatering & Pipeline Services Payment terms: 30 Days From Invoice Month-End (30 D F-I-M-E) ยท please quote PO-182113 / Claim 001 on remittancePO-182113 ยท Claim 001 ยท 1